Davidson County, I-24 Random on-call signatures on various interstates and interstates mm46.5 – 47 • Nightly, 8pm-5am, there will be nighttime partial ramp lane closures for Extrusion panel sigh installation.
Resurfacing on I-24, including bridge restoration from I-40 bifurcation to I-440 bifurcation, mm 51 – 53 • Daily from 9am to 3pm, between I-24 and I-40 will be There are multiple shoulder closure splits and an I-440 split for traffic circulation.
Random on call on various interstate and interstate highways, mm 48 – 48.5 • Nightly, 8pm – 5am, I-24 EB will close lanes for traffic diversion and construction activities.
Resurfacing on I-24 including bridge repairs from I-40 split to I-440 split, mm 51 – 53 • Nightly, 8pm – 5am There will be multiple alternate lanes on I Off and multiple alternate ramps off-24 between I-40 splits and I-440 splits.
Davidson County, I-40 Resurfacing on I-40 on Old Hickory Boulevard.To Arlington Ave (mm 216-217) • Every day (including weekends), there will be multiple alternating lane closures and multiple alternating ramp closures between Old Hickory Blvd on I-40 from 9am to 3pm .and Arlington Avenue.traffic loop.
Resurface on I-40 from Old Hickory Blvd.to Arlington Ave.• Every night (including weekends), from 8:00 p.m. to 5:00 a.m., multiple shoulders of I-24 between I-40 and I-440 will be closed for ITS work.
Davidson County, I-65 ITS Maintenance, mm 91.4 • Nightly, 8pm-5am and 2/28-3/1, I-65 NB will close three right lanes of seven, two Left lane (4 of 4) on ramp from Briley/Ellington to I-65 NB and rolling barricades to remove and replace DMS 6 north of Due West Ave.A left lane will also be closed on I-65 SB.This was planned for Thursday night, with Sunday night as a backup.There will be an exterior shoulder closure on I-65 in MM 91.4
Installation of Overhead Sign Structures on I-65 NB and SB (mm 96 – 97) • 2/28 and 3/1, I-65 NB and SB will close the right lane for delivery and construction of trusses.I-65 SB will have a right dual lane closure, I-65 NB will have a left lane closure, and rolling barricades with SB overhead trusses.Double right lanes will then be closed on I-65 NB, single left lanes will be closed on I-65 SB, and rolling barricades of NB overhead trusses will be set up.
Davidson/Rutherford County I-24 Intelligent Transportation System Construction and Upgrade from Nashville to Murfreesboro (Part 2), mm 53- mm80 • Nightly, 8pm.– At 5:00am, on the median strip from MM 53 to MM 65, EB and WB will close the left lane for overhead sign foundation work.Both lanes will remain open at all times.
I-65 grading, paving and bridges at the intersection of I-65 and SR99 in Murray County.• 2/26 – 2/28, 8 AM – 5 PM, alternate nighttime lane closures to repair damaged guardrail end treatments and repair potholes from recent snow and ice events.
ROBERTSON COUNTY, I-24 Random on call on various interstates and interstates, mm 19 – 20 • Nightly, 8pm – 5am, there will be nighttime lane closures to allow for the installation of extruded panels .
ROBERTSON COUNTY, I-65 Grading, Drainage, Construction of Bridges and Retaining Walls, ITS and Paving mm108 – 119 • Milling and paving operations nightly, 8pm-5am.North-South direction.Soldier to use.The ramps will be closed every night when activities are taking place in these areas.1 ramp will be closed at a time.The ramp will be operational again the next morning.
RUTHERFORD County I-24 Site Maintenance Paving • 3/1 – 3/2, 8 AM – 10 PM, will alternate lane closures for milling and paving activities to repair damaged asphalt sections.Both lanes will remain open at all times.
Measuring Drainage Inversions Along the Divider • Every night (excluding weekends) from 8:00pm to 5:00am, internal lane closures EB and WB will be measured within 1 mile on either side of SR 10 (Church Street).Traffic control will be provided by Advanced Traffic Control.
SUMNER COUNTY, I-65 Underground Drilling Operations for Geotechnical Engineering/Analysis, mm 98 – mm 105 • Nightly, 8pm – 5am, I-65 SB and NB will be intermittently closed for underground drilling Lane.
WILLIAMSON COUNTY I-840, BRIDGE REPAIRS OVER I-840 SOUTH GARRISON SERVICE MM 15.2 – 17.4 • 24/7, I-840 WB Lane will be closed for bridge repair work.WB traffic will be diverted to EB side lane 1 and all EB traffic will run on lane 2/shoulder.Two-way traffic for the entire project will remain in one lane.
Wilson County, Bridge Widening on I-40 on I-40 SR 171 – from 225mm to 226mm • Nightly, 8pm-5am, I-40 EB and WB intermittently close lanes for bridge widening activities .
Random on-call signatures on various interstates and interstates • Nightly, from 8pm to 5am, lanes will be closed at night to install extruded panel signs.
CHEATHAM COUNTY SR 455 SR 455 Slope, Drainage, Paving + Dike Construction (by others) • 24/7, continuous total road closure for levees (by others), box culverts, river relocation and road construction, from SR 49 to the AO Smith entrance.The entrance to Riverbluff Park will remain open to the public.Access to AO Smith from SR 12 will remain open.
Davidson County, SR 1 Resurfacing from SR 1 just south of Woodmont Avenue.(LM 13) to 15th Ave. (LM 17) • Nightly, from 8pm to 5am (including weekends), there will be multiple alternate lane closures for guardrail, concrete and utility adjustment operations.
Full and partial deep restoration of Portland cement concrete pavement and sidewalk on US 41 (US 70S, SR 1 Murfreesboro Road) from near Fesslers Lane (LM 20) to near Foster Ave (mm 20 – mm 20.32) 8pm Continuing from 10:00 to 5:00 am, Murfreesboro Rd lanes from Fesslers Lane to Foster Ave will be closed alternately to remove and refill damaged concrete.• Nightly, excluding weekends, the Murfreesboro Rd driveway from Fesslers Lane to Foster Ave is alternately closed from 8pm to 5am to clear damaged concrete.
DAVIDSON COUNTY, SR 6 Install overhead sign structure on US-31E (SR-6) (LM 10.90).• 2/28, 8pm – 6am SR 6 SB (Ellington Pkwy) will close right lane for delivery and construction of trusses • 3/2, 8pm – 6am SR 6 will close right lane SB, SR 6 Left lane closure on NB, and rolling barricades with elevated sign trusses.
Traffic Light Installation on SR 52 Ellington Drive, MACON County • From 9:00 am to 3:30 pm daily, lanes will be closed intermittently on SR 52 on Ellington Drive to install traffic lights.
Montgomery County SR 12 Bicycle and Pedestrian Facility mm16.8 – 19.3 • Sidewalk construction from 9am to 3pm daily.Contractor uses 1 driveway for security and construction.
MONTGOMERY COUNTY SR 13 includes: grading, drainage, construction of welded steel girder bridges, retaining walls and paving of SR 149 and SR 13 from River Road to Zinc Plant Road.MM 17-19 • Bridge works and/or paving work daily from 7am to 5pm.Mayhew Road will remain closed.Traffic on SR 13 will remain on the Phase 4 route when it opens on November 7, 2020.The width of the entire project is reduced to 22′.
Improvements at the intersection of SR 76 and SR 112 in Montgomery County.Grading, drainage and construction of retaining walls.• 9am to 3pm daily, grade work, lane closures will be intermittent
RUTHERFORD COUNTY SR 1 LPLM: Town of Smyrna Street Scapes on SR 1 • Construction activity will alternate lane closures daily from 9am to 3pm.
RUTHERFORD COUNTY, 266 From SR 102 (LM 5.0) to two concrete bulbous T-girder bridges on SR 266 (Jefferson Pike) east of I-840 (LM 9) grading, drainage, construction, signaling and paving.• Every day from 9:00 am to 2:30 pm, bridges over the Stones River will be marked for operation and short-term closure (5-10 minutes) beam setting operations.
SUMNER COUNTY SR 25 Gateway Drive Extension • The lanes near Barry Lane on SR 25 will be closed intermittently for road widening activities from 9 am to 3:30 pm daily.
SUMNER COUNTY, SR 174 LOCAL PROJECT: Goodlettsville Traffic Flow Improvement and Traffic Signal Upgrade • Eastbound SR-174 (Long Hollow Pk) before Caldwell Dr will be closed daily from 9am to 3pm to construct concrete islands and roads side ramp.
WILLIAMSON COUNTY SR 6 SR 6 (Franklin Road) from south of Moore’s Lane (LM 15.93) to Concord Road (18.53) – (mm 15.93 – 18.53) grading, drainage and paving – daily from 9am to 3pm, we Various construction activities, including paving and utility works throughout the road, intermittent traffic stops and/ Or temporarily close lanes (one direction at a time) items.We are planning extended delays and possible lane closures for construction activity on the following slip roads: Ashby Dr. Holly Tree Gap Rd, Long St., West Concord, Wikle Rd.and Mountain View Road.
WILLIAMSON COUNTY SR 96 LOCAL PROJECT: Sr-96 West Multi-Use Trail • Nightly, 8pm-5am, lanes will be closed on SR-106 to relocate grading, drainage, bridges and Semaphore building east of Arno Rd (LM 14.72) to SR 252 (Wilson Pk) (LM 20.62).• From 9 am to 3 pm daily, utility relocation and grading will close driveways and briefly disrupt traffic.
WILLIAMSON SR 106 Replacing 60″ Corrugated Metal Pipe on US 431 (SR 106) at MM 13.65 • SR 106 (Lewisburg Pk) between Carnton Ln and Eastern Flank Cir Continuous, continuous full circuit closure until June 30, with Replace culvert. Traffic will detour via SR 6 (Columbia Ave) and SR 397 (Mack Hatcher Pkwy). Detour signs will be in place.
Williamson County SR 397 SR 397 (Mack Hatcher Pkwy) grading, drainage, bridges, retaining walls, and paving from south of SR 96 to east of US 431 (SR 106) Daily from 9am to 3pm, there will be Temporary lane closures in both directions on Mack Hatcher on Hillsboro Road for a punch list project and northbound on Hillsboro Road for a punch list project.• On Highway 96W between Front Street and Boyd Mill Avenue, two-way lanes will be closed for checklist items daily from 9:00 am to 3:00 pm.A flag bearer will be used.
Bridge Widening on SR 171 on SR 171 I-40, WILSON County, mm 4.57 – 5.29 • Nightly, from 8pm to 5am, SR 171 will have intermittent lane closures for bridge widening activities.
Davidson County I-24 Emergency Pothole Repair • One-way alternating lanes and shoulder closures for emergency pothole repairs on I-24 in both directions from MM 32 to MM 36 daily from 9 am to 3 pm.• Every day at 9 am.– Single, alternating lanes and shoulders closed for emergency pothole repairs in both directions between I-24 at SR 171 OHB Exit and Haywood Lane Exit 57 at 3 p.m.
Davidson County I-40 Emergency Pothole Repair • Alternate single lane and shoulder closures in both directions on I-40 from McCrory Lane Exit 192 to SR 251 OHB Exit 199 from 9am to 3pm daily , for emergency pothole repairs.
Davidson County I-440 Emergency Pothole Repair • Ramps, driveways, and shoulders on I-440E at I-65 S are closed daily for emergency pothole repairs from 9 am to 3 pm.
ROBERTSON COUNTY I-65 EMERGENCY PAVING NB & SB • From 8 am to 10 pm daily, lanes will be closed alternately for milling and paving activities to repair damaged asphalt sections.One lane will remain open at all times.
RUTHERFORD County I-24 Field Maintenance Paving mm 89-96 • 2/28 – 3/2, 8am – 10pm, lanes EB and WB will be closed alternately for milling and paving activities to repair damage of asphalt roads.One lane will remain open at all times.
Smith County, I-40 Emergency Pave in situ on I-40 in Smith County • I-40 EB and WB will intermittently close driveways for emergency paving activities from 8am to 10pm daily mm 250 – 258.
RUTHERFORD County I-840 Site Maintenance Paving • From 8 am to 10 pm daily, the driveway will be closed alternately for milling and paving activities to repair damaged asphalt sections.One lane will remain open at all times.mm 55 – 62
Davidson County SR 155 Milling and Paving • All EB lanes and SR 55 shoulders are alternately closed from Cumberland River Bridge to Gallatin Rd from 9am to 3pm daily.For milling and paving.• Various lanes and shoulders of SR 155 westbound are closed for milling and paving daily from 9 am to 3 pm.
Davidson County SR 1 Road Maintenance/Repair • Alternating lanes and shoulder closures in both directions from Vine Ct. to Harding Pike daily from 9:00 am to 3:00 pm.Go to Woodlawn Dr. for road repairs and repairs.
DAVIDSON COUNTY SR 24 Road Repairs • Alternating lane closures for road repairs in Charlotte Pike from 51st to 28th Avenues daily from 9:00 am to 3:00 pm.• Single alternating WB lane closures daily for milling and resurfacing on Lebanon Pike, 200′ east of Spence Lane, from 9am to 3pm.
Motorists are encouraged to exercise caution and observe reduced speed limits in all TDOT work areas, regardless of lane closing activity.The information in this report was provided by the contractor to the Department of Transportation.Most jobs are weather dependent and subject to change due to severe weather.
Get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic from your desktop or mobile device.Travelers can also dial 511 from any landline or cell phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel.
As always, drivers are reminded to use all driving information tools wisely and know before you go!Check travel conditions before heading to your destination.Drivers should not use their mobile phones to tweet, text or talk while driving.